November 19, 2025: Unique ribbon cutting event at Schickler Elementary celebrates new driveway

To celebrate the new driveway at Schickler Elementary, a ribbon cutting was held where fourth-grade students at the school ran through ribbons instead of the traditional ribbon cutting with scissors. It was a very fun day and the weather cooperated! For photos and videos, click the link below. Schickler Drive Ribbon Cutting – Nov. 19,…
-
September 22, 2025: RTU installed on roof of new LHS auditorium lobby

Today, a new RTU (rooftop unit) was installed on the roof of what will be the new auditorium lobby at Lapeer High School. An RTU is a self-contained, all-in-one HVAC system that provides heating, cooling, and ventilation for commercial buildings by housing all components, such as the compressor, coils, fans, and heating elements, within a…
-
July 31, 2025: New LHS chiller, lighting, fire suppression units, choir room flooring installed, work continues on auditorium

As the calendar turns to August, district bond work is continuing across Lapeer Community Schools. On July 31, the new chiller/air conditioning unit was installed at Lapeer High School. In addition, new lighting continues to be installed at LHS, work is moving along on the new auditorium, and fire suppression units have been installed as…
-
June 23, 2025: Summer work at LHS starts with new auditorium lobby construction, north parking lot milling

With school out and summer here, bond work at Lapeer High School has kicked into high gear. The new lobby for the new auditorium/performing arts center has started, as has the milling work on the north parking lot in preparation for that lot to be paved later this summer. As a reminder, Lapeer High School…
-
Dec. 19, 2024: Bond update, District reconfiguration update

LCS Community – As the bond work continues throughout the 2024-25 school year at many Lapeer Community Schools buildings, we want to provide another update with you on how the work will coincide with the district’s planning for the reconfiguration that will take place for the 2025-26 school year. As a reminder, the 2025-26 school…
-
October 31, 2024: Bus Garage parking lot paved, multi-purpose rooms nearing completion, LHS science labs moving along

As the school year is in full swing and many major projects were completed over the summer, there is still bond work happening during the school year. First, employees at the Bus Garage want to thank the community that passed the bond in 2022. With that, the Bus Garage now has a freshly paved parking…